With the aim of increasing the operating capacity of the South Wastewater Treatment Plant, addressing flooding and environmental pollution in the North of the city, improving environmental sanitation, enhancing flood drainage and preventing landslides on both sides of Cai river in combination with upgrading transport infrastructure to meet the city's development needs as planned. On August 26, 2019 Khanh Hoa Development Project Management Unit signed NT1.3 contract package with Ngu Thuong Engineering - Construction Corporation: Constructing pumping station, separation well and sewer system of level 1, 2, 3 under Coastal cities' Sustainable Environment Project - Nha Trang subproject.
The project includes 04 components.
• Component 1: Expanding sanitation infrastructure.
• Component 2: Improve urban connectivity.
• Component 3: Clearance and resettlement.
• Component 4: Technical assistance and institutional reform.
On October 2019 Coastal cities' Sustainable Environment Project - Nha Trang subproject officially started construction by Ngu Thuong Engineering - Construction Corporation as the main contractor right after being supervised by the Supervision Consultant.
It is expected that in the middle of February 2021, it will be inaugurated and put into official operation.
Project Summary:
Project: Coastal cities' Sustainable Environment Project - Nha Trang subproject
Location: Nha Trang City, Khanh Hoa Province
Main contractor: Ngu Thuong Corp
Progress: 10/2019 - 02/2021

Contract signing ceremony
TBM morning before starting work
Manholes were constructed
Construction, earthworks, welding and installation of HDPE pipes
The contractor reports the construction situation
Construction of compaction and return of plastic mats
Construction of TB3 pump station in Thap Ba
Construction of the Cu Huan route during the social gap due to Covid-19 epidemic
World Bank delegation checks on the site
Construction of HDPE D400 pipeline
Construction work of HDPE D200 pressure pipe
Construction of TB1 pumping station