Phuoc Long Apartment and Service Area - Imperium Town - Converging quintessence & Worthy of class

Located in the center of southern Nha Trang, Imperium Town Nha Trang is not simply a high-end serviced apartment complex but also a proud symbol that stands out in the heart of the vibrant coastal city.


On a total area of more than 10,168 square meters, Imperium Town Nha Trang is the perfect combination of trendy Shopvillas and the luxurious and splendid Imperium Tower. It is a place that not only converges values ​​to create perfect apartments but is also an ideal vacation destination. Each resident at Imperium Tower will have for themselves a universal "key" to enjoy life to the fullest, so that every moment of life is always full of energy and unforgettable impressions. (Extract information from the Investor).

Project planning: Including 39 floors with 561 luxury apartments, 3 floors of commercial podium, 3 floors of basement parking, 36 floors of apartments, Commercial Avenue with 41 trendy Shopvillas, with a total investment capital of up to 1,200 billion VND. On April 27, 2020, the Investor signed a contract for the package "Construction and installation of reinforced concrete structures of the Imperium building" with Ngu Thuong Construction Engineering Joint Stock Company. Immediately after that, construction work officially began to ensure the project officially comes into operation in mid-May 2021.


Summary of project information:

Project: Phuoc Long Apartment and Service Area – Imperium Town
Location: Nha Trang city, Khanh Hoa province
Main contractor: Ngu Thuong Construction Engineering Joint Stock Company
Progress: April 2020-May 2021

Công việc thi công chính thức bắt đầu ngày sau khi chiến dịch giãn cách xã hội chống covid-19 kết thúc
Construction work officially began the day after the social distancing campaign against covid-19 ended
Họp nhanh phối hợp ngay tại công trường giữa Ban QLDA, TVGS và Nhà thầu Ngũ Thường
Quick coordination meeting right at the construction site between the Project Management Board, Supervision Consultant and Ngu Thuong Contractor

Công tác thi công đào đắp,hàn ống và lắp đặt ống HDPE
The construction work was promptly implemented by Contractor Ngu Thuong according to approved methods, with the close participation of Supervising Consultants and Project Management Board.


The concrete pouring site completed floor B2

Sàn B1 đã lên hình
The next progress milestones of basement B2 are implemented closely according to progress


Safety and Site Inspections are carried out in compliance


Floor B1 has appeared