As informed about the project, in February 2019, the Solar Park1 and Solar Park2 solar power plant projects were officially started construction on an area of 118 hectares in Hamlet 3, Binh Hoa Nam commune, Duc Hue district, Long An province by the Joint Venture Syouei (Japan) - TWT (Thailand) - Ngu Thuong - EEA (Vietnam) with sponsorship from Nam A Bank and other banks.
 
By June 30, 2019, the project was officially connected to the grid to sell electricity to EVN, providing clean, green energy for the locality as well as for the entire Southern power network.

 

Immediately after the two factories Solar Park 1 and Solar Park 2 come into operation, Vietnam Solar Joint Stock Company and its partner contractors will immediately begin preparing to continue constructing the factories Solar Park 3, Solar Park 4 and Solar Park 9 respectively, promising to promote the advantages to further improve quality, contributing more and more to the work of building and strengthening national energy security.

0 / 5 (0binh_chon)
Comment
Submit a comment
    Comment

    Related articles

    Why did the WTC twin towers collapse?

    Why did the WTC twin towers collapse?

    World Trade Center Twin Towers     With its pride, the World Trade Center Twin Towers - World Trade Center (WTC) in New York shocked everyone who knew it during the events of ...