With the purpose of storing reserve goods to meet market demand, the Investor has aimed to build a Warehouse with full functionality and modern design at Dien Phu Industrial Cluster, Dien Phu Commune, Dien Khanh District, Khanh Hoa Province.
The Warehouse of Thang Long Construction Trading Service Joint Stock Company has a construction area of 9,000 m2, including Warehouse - Office and other auxiliary works.
In order to quickly deploy the project, in October 2020, the Warehouse construction project officially began construction immediately after being issued a groundbreaking order by CDT, implemented by Ngu Thuong Construction Engineering Joint Stock Company as the main contractor. Project construction time is expected to be 5 months.
Summary of project information:
Project: THANG LONG WAREHOUSE
Location: Dien Phu Industrial Cluster, Dien Phu Commune, Dien Khanh District, Khanh Hoa Province
Main contractor: Ngu Thuong Construction Engineering Joint Stock Company
Progress: October 2020 - April 2021
![]()
Project commencement

Live safely at the beginning of every working hour
![]()
Construction of PHC D300 pile pressing
![]()
Construction of foundations and beams in stormy weather

Steel columns and trusses are erected after the foundation is completed

The corrugated iron roof was covered one by one

Compaction of the Warehouse floor

Concrete work to complete the Warehouse floor
![]()
Fire Prevention and Fighting Construction Work

The construction of the operating house serves the future management of the Warehouse
![]()
Construction work of storm water drainage system D400
![]()
Construction work of leveling and compacting internal roads

Internal road concrete construction work
![]()
Fire protection and acceptance work

Acceptance work of the Department of Construction
Overview of the project and construction process