Thursday - April 25, 2013 13:52
Nokia Vietnam Vietnam mobile phone equipment factory was built in VSIP Bac Ninh Industrial Park with an area of 17 hectares, with a total initial investment of 200 million Euro (equivalent to 300 million USD). This is Nokia's first factory in Southeast Asia and the company's 11th mobile phone production facility globally. At VSIP Bac Ninh Industrial Park, Nokia will participate in manufacturing, processing and assembling mobile phones. It is expected that the factory will officially come into operation in 2013, with an output of 180 thousand products/year, creating jobs for 10 thousand workers.

Factory in Bac Ninh
Currently, Nokia has a high position in developing economies, thanks to the diversity of basic phone lines. The construction of a Nokia mobile phone factory in Vietnam not only meets the increasing demand for basic phones of people, but also helps Nokia implement its strategy "Connect with the next billion people” globally.
Nokia first came to Vietnam in 1996. Currently, the Finnish phone company has 10 manufacturing factories from Latin America (Brazil and Mexico) to Europe (Hungary, Romania, Finland, England) and Asia (India, China and Korea).
-------------------------------------------------------------------------------------------
Project: Nokia Vietnam mobile phone equipment factory
Location: VSIP Bac Ninh Industrial Park
Investment capital: 200 million Euro (equivalent to 300 million USD).
Total factory area: 17 hectares
Construction time: 2012 - 2013
Customer: POSCO ENGINEERING
At once, the construction site had several hundred workers. Even though the field is empty, safety work is highly demanded from Mace Consulting. Even the shirts must have reflective tape. This caused the uniforms to be damaged at first because they had not yet been able to provide shirts with reflective tape to the construction site.

Safe! Safe! Safe!

Foundation "matrix".

Prepare for the first batch of concrete for the ground floor
July 2012
Three months later, from an empty lot, the appearance of the construction site was clear with the Amenity area completing concrete on the first floor and the Factory area also starting to concrete the first floor. In just a short time, the silhouette of a factory will gradually appear.

Amenity area has completed the first floor.

Column on the 1st floor of the Factory area

Some steel structure work has begun.
September / 2012.
“Hurry and urgent” are words to clearly express the image of the construction site during this period.
Overcoming the harsh summer sun and winter cold, the project has completed 3/4 of the way and is waiting for the opening day.

The Nokia sign was hung up at Amenity's house
The atmosphere that can be felt at the construction site, all the echoes mixed together in the construction site, makes everyone more enthusiastic about their work and racing to do it.
The Nokia sign was hung up in the Amenity area, increasing everyone's excitement to compete to reach the finish line.

Everyone is racing to reach the finish line
None other than the workers with hammers and nails, who hurriedly worked rhythmically like construction site artists to create Nokia's finished products today.
Amenity executive building will be handed over soon next month, Nokia officials and employees have also prepared their personal belongings and luggage to move into the new work area to start the journey ahead.
Through day and night, all contractors were determined to complete the requirements given by the Investor.
The structure will be completed by the end of March 2013 with cleaning and handover.

Artists are dancing on scaffolding over 10 meters high every day

The 5T bucket crane cleaning materials and bringing them to the warehouse became small
March 2013