In the context of increasing demand for electricity, plus encouragement from the government, Royal Group decided to invest in the field of solar power.
Phase 1 with a 100MW plant has been implemented with research and construction contract negotiations in the last days of 2018.
In February 2019, the Solar Park1 and Solar Park2 solar power plant projects were officially started construction on an area of 118 hectares in Hamlet 3, Binh Hoa Nam commune, Duc Hue district, Long An province by Joint Venture Syouei (Japan) - TWT (Thailand) - Ngu Thuong - EEA (Vietnam). The rated capacity of a Factory is 50MW; Connection voltage 110kV.
It is expected that by the end of June 2019, it will be inaugurated and officially put into operation.
Summary of project information:
Project: VIETNAM SOLAR Solar Power Plant
Location: Duc Hue District, Long An Province
Main contractor: Joint Venture Syouei(Japan) – TWT(Thailand) – Ngu Thuong – EEA (Vietnam)
Progress: February 2019-June 2019

EPC contract signing ceremony

Safe activities at early hours

Pile acceptance test before putting into construction

Pile foundation

Installing the support frame from April 2019

The battery wing is in the assembly stage

Put the inverter into position

110KVA transformer station

110KVA transformer station

Time is short so many jobs have to be done at night
Check before handing over the factory

Solar panels look quite simple
Panorama of the factory

110kV transformer station, where electricity is transferred to the grid

The Deputy Prime Minister looks after the souvenir tree during his visit to the project