Package NT-1.7: Construction of a wastewater treatment plant in the North; Supply and installation of mechanical equipment for wastewater pumping stations.
- Wastewater treatment capacity: 15,000m3/day.
- Using deep oxidation ditch technology.
- The total construction area is 5.4 hectares, of which the factory is 3.03 hectares and the buffer zone is 2.37 hectares.
Location: Nha Trang city, Khanh Hoa province
Main contractor: Joint venture of Ngu Thuong Engineering - Construction Joint Stock Company and Seen Engineering Joint Stock Company.
Progress: 18 months from the date of commencement.
With the goal of increasing the operating capacity of the Southern Wastewater Treatment Plant, solving flooding and environmental pollution in the Northern area of the City, improving environmental sanitation, enhancing flood drainage and preventing landslides on both sides of the Cai River, combined with upgrading transportation infrastructure to meet the city's development needs as planned. On October 27, 2021, Khanh Hoa Provincial Development Project Management Board signed a contract for package NT-1.7 with the Joint Venture of Ngu Thuong Engineering - Construction Joint Stock Company and Seen Engineering Joint Stock Company: Construction of the Northern wastewater treatment plant; Supply and installation of mechanical equipment for wastewater pumping stations under the project Sustainable Environment for Coastal Cities - Nha Trang Subproject.
The project includes 04 components.
- Component 1: Expand sanitation infrastructure.
- Component 2: Improve urban connectivity.
- Component 3: Land clearance and resettlement.
- Component 4: Technical assistance and institutional reform.
In December 2021, the project Sustainable Environment for Coastal Cities - Nha Trang Subproject officially began construction immediately after the Supervision Consultant issued a groundbreaking order, with the Joint Venture Company Ngu Thuong Engineering - Construction Joint Stock Company and Seen Engineering Joint Stock Company being the main contractor.

Overall project perspective: Northern Wastewater Treatment Plant

Project groundbreaking ceremony

TBM every morning before starting work

Organic clearing and excavation work

Pile pressing construction work

Construction of car and motorbike garages

Construction of Sedimentation Tank at the end of 6.1.1 and 6.1.2

Construction of sludge tank and sludge pumping station 13-13.1

Construction of water separation and sludge thickening house 14

Construction of grease storage tank

Construction of electricity distributor 17

Construction of valve15 saliva collection tank

Construction of gravity condensation tank 12.2.1-12.2.2
During the construction process, the contractor raised large rocks underneath the structural items. The strong attention and direction of the Project Management Board and supervision consultant required the design unit to adjust technical handling so as not to affect the construction progress.

Rocks at the Oxygen Ditch and Gravity Sludge Thickener

Construction of 5.1 v oxygen tankah 5.4.2
Because the site clearance work has not been completed, the residential road has not been removed from the construction site, the contractor maintains road irrigation work to ensure environmental hygiene.

Road irrigation reduces dust during construction
On May 19, 2022, Vice Chairman of the Provincial People's Committee inspected the construction progress and progress of site clearance and relocation of technical infrastructure.

The Contractor reports to the Chairman of the People's Committee of Khanh Hoa Province Nguyen Anh Tuan
On June 2, 2022 and August 4, 2022, the World Bank delegation inspected the construction site.

The contractor reports construction progress and obstacles to the site and technical infrastructure

HDPE pipe construction work of the package.
Accelerating the progress of the sustainable environmental project in coastal cities - the Nha Trang subproject is an extremely urgent issue, but the work of site clearance and relocation of technical infrastructure is still too slow. Attached is the link to the reportage conducted by Khanh Hoa television station.
August 28, 2022 Government working group led by Minister of Finance Ho Duc Phoc visit construction site.

The contractor reports construction progress and disbursement output

Overall construction site updated until September 30, 2022