Saturday - April 27, 2013 09:19
The wastewater treatment plant in the south of Nha Trang city belongs to category 02, phase 2 of the Nha Trang city environmental sanitation improvement project with a total expected investment of nearly 25 million USD, sponsored by the World Bank and counterpart capital of Khanh Hoa province.
According to the design, the plant is the place to receive and treat all wastewater from the central and southern areas of Nha Trang city with a design capacity of 40,000 m3 day/night and is expected to be upgraded to 60,000 m3 day/night by 2025. All wastewater here will be treated using deep oxidation ditch technology - an advanced wastewater treatment technology that has been widely applied in many countries around the world. The project is a very important item in the environmental sanitation improvement project of Nha Trang city. When the project comes into operation, it will stop the long-standing practice of directly discharging untreated wastewater into Nha Trang Bay.

Welcoming guests to the groundbreaking ceremony
On the morning of August 17, the Management Board of the Nha Trang City Environmental Sanitation Improvement Project, main contractor Kumho and subcontractor Ngu Thuong held a groundbreaking ceremony to build the "Southern Nha Trang City Wastewater Treatment Plant". Mr. Nguyen Chien Thang - Chairman of the Provincial People's Committee and leaders of departments, branches and Nha Trang city attended.

Basic equipment is ready for construction
Ngu Thuong Company will be responsible for all construction work for the project. The necessary machinery has also been deployed to enable construction immediately after the groundbreaking ceremony. Because the project is located on a large shrimp pond area, the project milestone handover was also carried out one week before the groundbreaking ceremony to take advantage of time right after the start of construction.

The group handed over markers across the country for a kilometer to check the markers

The Project Management Board and the contractor relaxed a bit under the Central region's sun

Mold is buried deep underground
----------------------------------------------------------------------------------------------------------------
Project: Nha Trang City wastewater treatment plant
Location: Phuoc Dong commune, City. Nha Trang
Investment capital: 25 million USD
Total factory area: 60 hectares
Construction time: 2012 – 2014
Investor: Nha Trang City Environmental Sanitation Improvement Project Management Board
September 2012
One month after the groundbreaking ceremony, the silhouette of rice fields and shrimp ponds in the brackish water area has gradually changed to the image of a construction site in the stage of clearing the ground.
Nha Trang is not yet the center of the Central region, but the rain in the Central region has shown itself at WWTP. The other thing is that not only is it "dirty" but the ground looks very sturdy after the sun comes up, but... don't step on it.

It is quite "abysmal" to enter the construction site through the newly completed access road

The Caterpillar became small, in the distance was Nha Trang city
October 2012
After the long holidays of Tet, the construction site is bustling again with pile work and starting foundation work for the last 4 sedimentation tanks.

Each convoy of trucks carrying piles followed each other into the construction site.

Shaping the bottom of the final settling tank

HDPE pipes are also prepared to be installed at the bottom of the tank

Internal acceptance
Official acceptance of steel before pouring concrete

Construction site at the end of March 2013
Reinforcing steel for the bottom of one of the 4 final settling tanks
Formwork work to form the final settling tank

Panoramic view of the construction site at the end of June
----------------------------------------
One year

Management experience workshop presented by contractor NT-2.1.
In May 2013, the World Bank conducted an inspection of the entire Nha Trang City Environmental Sanitation Improvement project. The quality of the project and the professional working style of the Wastewater Treatment Plant project, package NT-2.1, have been highly appreciated by the World Bank and the Project Investor has been suggested to replicate it in other packages. On the occasion of one year of signing the contract, the Investor and contractor of package NT-2.1 organized a workshop to share experiences with contractors of other packages of the project. The People's Committee of Khanh Hoa - Nha Trang Province, the Department of Construction and other departments of Nha Trang - Khanh Hoa are also satisfied with the quality and progress of the project and request the contractor to continue the initial success until the project is completed.


The shrimp ponds are gradually being replaced after 10 months of work.
Panoramic view of the construction site at the end of September 2013
--------------------------------------------------------

Panoramic view of the construction site at the end of November 2013
View of the construction site in early April 2014 after the main work was completed
Engineer Ngu Thuong and the Management Board guided students to visit the factory during trial run
----------------------------------------
After nearly 30 months of construction, on November 7, 2014, the factory was inaugurated after a trial period and achieved results according to design.

Members of two companies Kumho and Ngu Thuong before parting ways with the project

View of the factory on inauguration day
Wastewater before passing through the final settling tank
Images from Google were updated a month after the inauguration
Although greatly affected by the bad weather of the rainy season in central Vietnam this year, according to information from the Investor during the inspection of the ENVIRONMENTAL SANITATION IMPROVEMENT PROJECT FOR COASTAL CITIES in the three cities of Nha Trang - Quy Nhon - Dong Hoi, NT-2.1 was assessed by the World Bank as a typical bidding package in terms of quality management and progress of the entire project.