GENERAL INTRODUCTION ABOUT THE PROJECT
PROJECT: RESIDENTIAL AREA, HIEP BINH PHUOC ENTERTAINMENT PARK, THU DUC.
WORKS: DAI NHAT LAKE WATER MUSIC
PROJECT ITEMS: STRUCTURAL CONSTRUCTION – WATER MUSIC FLOOR MEP
TYPE OF CONSTRUCTION: AGRICULTURAL AND RURAL DEVELOPMENT WORKS (Irrigation works)
SCALE OF THE PROJECT
- INVESTOR: VAN PHUC REAL ESTATE GROUP/ DAI PHUC REAL ESTATE JOINT STOCK COMPANY
- CONSTRUCTION CONTRACTOR: NGU THUONG CONSTRUCTION TECHNICAL JOINT STOCK COMPANY
- Investment capital: more than $5.0 million
- Construction progress April 20, 2021 to March 2022
- Floor area 8,000 (m2.
- Required altitude :+0.00 (m), according to national altitude

Moving 60T barge equipment into Dai Nhat lake

Morning activities


Laser piling work in the middle of Dai Nhat lake

Sand pumping work for the construction of the water music floor

Piling work on water music floor


The work of moving objects to the middle of Dai Nhat lake

Soil preparation and pouring concrete lining

Construction work of water music floor structure

Construction at night

Water music floor seen from above

Construction of dredging Dai Nhat Lake, handover and operation
Operate the water music floor
Author: Tuan Khanh


Comment