Saturday - June 27, 2020 08:00
With the goal of increasing the operating capacity of the Southern Wastewater Treatment Plant, solving flooding and environmental pollution in the Northern area of the City, improving environmental sanitation, enhancing flood drainage and preventing landslides on both sides of the Cai River, combined with upgrading transportation infrastructure to meet the city's development needs as planned. On August 26, 2019, Khanh Hoa Provincial Development Project Management Board signed a contract for package NT1.3 with Ngu Thuong Engineering - Construction Joint Stock Company: Construction of pumping stations, separator wells and wastewater drainage networks of levels 1, 2, 3 under the project Sustainable Environment for Coastal Cities - Nha Trang Subproject.
The project includes 04 components.
- Component 1: Expanding sanitation infrastructure;
- Component 2: Improving urban connectivity;
- Component 3: Site clearance and resettlement;
- Component 4: Technical assistance and institutional reform.
In October 2019, the project Sustainable Environment for Coastal Cities - Nha Trang Subproject officially began construction immediately after receiving the order to start construction by the Supervision Consultant with Ngu Thuong Construction Engineering Joint Stock Company as the main contractor.
It is expected that around mid-February 2021, it will be inaugurated and officially put into operation.
Summary of project information:
Project: Sustainable environment for coastal cities - Nha Trang subproject
Location: Nha Trang city, Khanh Hoa province
Main contractor: Ngu Thuong Construction Engineering Joint Stock Company
Progress: October 2019-February 2021

Contract signing ceremony

Morning exercise before starting work
Manholes are constructed at the yard
Excavation and earthwork construction, pipe welding and HDPE pipe installation
Contractor reports on construction status
Construction work of compaction and return of plastic mats
Construction work of TB3 pumping station at Thap Ba
Construction work on Cu Huan road during the social distancing period due to the Covid-19 epidemic
The World Bank delegation inspected the reality at the construction site
Construction work of HDPE D400 pipe line
Construction work of HDPE D200 pressure pipe
Construction work of TB1 pumping station
With the nature of the work and the weather in Nha Trang preparing for the rainy season, the Contractor focuses on human resources and equipment to complete the work.

Construction work at alley 41 Duong Hien Quyen (A difficult location of the project).

Construction work at Gieng Tach No. 01.

Complete construction work of asphalt concrete.
With our efforts, the project was also completed with the set goals and ahead of schedule compared to the contract.

The end!
TProject news on Khanh Hoa News