Construction of wastewater treatment plant in the North – Nha Trang subproject
Tuesday - 04/10/2022 10:15
Project: Sustainable environment in coastal cities – Nha Trang subproject.
Package NT-1.7: Construction of wastewater treatment plant in the North; supply and install mechanical equipment for wastewater pumping stations.
- Waste water treatment capacity: 15,000m3/day.
- Using deep oxidation ditch technology.
- The total construction area is 5.4 ha, of which the factory is 3.03 ha, the buffer zone is 2.37 ha.
Location: Nha Trang City, Khanh Hoa Province
Main Contractor: Joint Venture Ngu Thuong Construction Engineering Joint Stock Company and Seen Engineering Joint Stock Company.
Progress: 18 months from the date of commencement.
With the goal of increasing the operating capacity of the Southern Wastewater Treatment Plant, solving flooding and environmental pollution in the northern part of the city, improving environmental sanitation, and enhancing flood drainage capacity. and anti-erosion on both sides of Cai River in combination with upgrading transport infrastructure to meet the city's development needs as planned. On October 27, 2021, the Khanh Hoa Provincial Development Project Management Board signed a contract for NT-1.7 package with the Joint Venture Ngu Thuong Engineering - Construction Joint Stock Company and Seen Engineering Joint Stock Company: Construction construction of a wastewater treatment plant in the North; supply and installation of mechanical equipment for wastewater pumping stations under the Sustainable Environment in Coastal Cities project - Nha Trang Subproject.
The project consists of 4 components.
- Component 1: Expanding sanitation infrastructure.
- Component 2: Improving urban connectivity.
- Component 3: Site clearance and resettlement.
- Component 4: Technical assistance and institutional reform.
In December 2021, the sustainable environment project in coastal cities - Nha Trang sub-project officially started construction right after the construction order was issued by the Supervision Consultant by the Joint Venture Company of Engineering Joint Stock Company. – Ngu Thuong Construction and Seen Engineering Joint Stock Company are the main contractors.
Overall perspective of the project: Northern Wastewater Treatment Plant
Commencement ceremony of the project
TBM every morning before starting work
Luminescence and organic excavation work
Pile pressing construction work
Construction of garages for cars and motorbikes
Construction of 6.1.1 and 6.1.2 . End Sedimentation Tanks
Construction of sludge tank and mud pumping station 13-13.1
Construction of 14 . water separator and sludge concentrator
Construction of oil storage tank
Construction of 17 . power distributor
Construction of saliva collection valve 15
Construction of gravity concentrator tank 12.2.1-12.2.2
During the execution of the construction, the contractor towed the large rocks located below the structural items, the intense attention and direction of the PMU and the Supervisory Board requested the design unit to adjust the technical handling to prevent damage. affect construction progress.
Rocks at the Oxygen Ditch and Gravity Mud Concentration Tank
Rocks at the Oxygen Ditch and Gravity Mud Concentration Tank
Because the site clearance has not been completed, the residential road has not been moved out of the construction site, the contractor maintains road irrigation to ensure environmental sanitation.
Road irrigation to limit dust during construction
On May 19, 2022 Vice Chairman of the Provincial People's Committee checked the construction progress and the progress of site clearance and relocation of technical infrastructure.
Contractor reports to Vice President of Khanh Hoa Provincial People's Committee Nguyen Anh Tuan
On June 2, 2022 and August 4, 2022 World Bank delegation inspected the construction site.
Contractors report construction progress and obstacles to site and technical infrastructure
Construction of HDPE pipes of the package.
On August 28, 2022 Government delegation led by Finance Minister Ho Duc Phuc visited the construction site.
Contractor reports construction progress and disbursed output
The overall construction site updated until September 30, 2022
Report on the Bac Nha Trang Wastewater Treatment Plant by Khanh Hoa Television
Author: Nguyen Tan
Newer news
Manufacturing factory of KURZ Vietnam Co., Ltd
13:36 18-07-2023
KURZ Vietnam Co., Ltd officially started the construction of a factory area of 60,000 m2 (with a total area of 120,000 m2) at Becamex Binh Dinh Industrial Park, Nhon Hoi Economic Zone, Van Canh district.
DetailsCoastal Cities Sustainable Environment Project – Quy Nhon sub-project
08:44 07-03-2023
Contract QN-1.9: Sewer system of level 3, pump station and pressure sewer system The contract was signed on February 24, 2023 with a period of 12 months. Right after contract signing Ngu Thuong Corp. immedietly start the work with target to complete site works within 10 months.
DetailsLeveling Residential Area, Hiep Binh Phuoc Amusement Park
15:52 20-02-2023
Residential area of Hiep Binh Phuoc amusement park with a scale of 26.4 ha is one of 6 component projects in the overall project of Van Phuc urban area with 198 ha Hiep Binh Phuoc amusement park located on Hiep Binh Phuoc ward, Thu Duc city, the western gateway of Ho Chi Minh City. The project has a convenient location, 7 km from the city center, 8 km from Tan Son Nhat airport and attached to many important traffic routes such as National Highway 13, Pham Van Dong Boulevard.
DetailsManufacturing factory of KURZ Vietnam Co., Ltd
11:51 24-10-2024
With the motto of creating environmentally friendly products and reducing CO2 emissions, the Investor decided to install a solar power system with a capacity of 1.4 mWp.
DetailsTon Dong A Factory – Thu Dau Mot
12:47 12-10-2024
Ton Dong A has decided to invest in a rooftop solar power system for self-consumption, with a total solar system capacity of 3.448 MWp. Contractor Ngũ Thường is responsible for the CK5 workshop, which has a capacity of 1.24 MWp.
DetailsOlder news
Water music of Dai Nhat lake - Van Phuc residential area, Ho Chi Minh
15:39 23-08-2022
Water Music Project in Van Phuc residential area is a unique utility project designed according to European technology, with 50 multi-purpose nozzles creating a water column up to 80m high, with a total length of 130m . This place combined with Diomond Square with a capacity of 10,000 people and other utility works on Dai Nhat Lake will bring an extremely unique entertainment and entertainment complex at Van Phuc Residential Area - Ho Chi Minh City.
DetailsSand leveling of Phuoc Loc - Nha Be project
11:20 26-08-2021
Phuoc Loc - Nha Be project is located in Phuoc Loc commune, Nha Be district, Ho Chi Minh City with an area of ~ 50 hectares with a total volume of 1.4 million m3 expected to be completed in 2021.
DetailsConstruction of Thang Long warehouse
15:56 23-07-2021
In October 2020, the warehouse construction project officially started construction right after being issued the ground-breaking order by the Investor, performed by Ngu Thuong Engineering – Construction Corporation as the main contractor.
DetailsThe project to build factory and the main warehouse NFC Food Co., Ltd
11:59 13-05-2021
On November 2018 The project to build factory and the main warehouse officially was started construction right after the investor issued the groundbreaking order, by Ngu Thuong Engineering - Construction Corporation as the Design & Build main contractor